Answer

The top row of a collapsible budget line is a placeholder and doesn't constitute the amount budgeted for that fund, but adds together the lines below and to the side in the Budgeted Column.  If there are rows under the drop down menu for a particular Fund that contain dollar amounts, the amount in the Budget Column for that fund should be 0.00.  This will stop the Total Fund Budget column from displaying an incorrect amount.

Additional information

For more information please see the Budgets page for WorldShare Acquisitions.